Paving Program
The paving program is weather-dependent, typically beginning in the spring and continuing until early fall each year. The paving (capping) program is largely based upon priorities identified by the pavement management system. Call 604-276-4189 to report a road that is considered in extremely poor condition.
Residents directly fronting the roads listed will be notified by our contractor that paving is scheduled in their area. Ensure that vehicles are not parked or obstructing the road during paving. The suggested schedule is subject to change without notice.
2022 Proposed Paving Program
Proposed Paving Locations | Proposed Schedule |
---|---|
No. 6 Road Hwy 91 Underpass-Maycrest Way |
October/November 2022 |
Great Canadian Way Sea Island Way - Bridgeport Road |
October/November 2022 |
Fraserwood Place Westminster Hwy - Gordan Way |
October/November 2022 |
Finlayson Drive Gagnon Place - McLennan Avenue |
October/November 2022 |
7000 Block No. 3 Road (Granville Avenue - Blundell Road) |
In Progress |
Great Canadian Way (River Road - Bridgeport Road) |
October/November 2022 |
11000 Block Steveston Hwy (Shell Road - Coppersmith Place) - 40% RAP |
2023 |
Westminster Hwy (Gilley Road - Boundary Road) |
2023 |
18000 Block River Road (No. 8 Road - Nelson Road) |
2023 |
River Drive WBL (No. 4 Road - Van Horne Way) |
2023 |
Mitchell Road (120m south of Elburne Way - Twigg Place EOP East end) |
2023 |
12000 Block Blundell Road (No. 5 Road - Sidaway Road) |
2023 |
Douglas Crescent, Wellington Crescent, Wellington Avenue, Handley Avenue, Catalina Crescent, Anson Avenue |
2023 |
2023 Proposed Paving Program
Proposed Project Location |
Proposed Schedule |
---|---|
12000 Westminster Highway (No.5 Rd – MOTI) – including the No.5 Road Intersection | 2023 |
9000 Block Cambie Road (Garden City Road – No.4 Road) including both intersections | 2023 |
10000 Block No.6 Road (Steveston Hwy – Triangle Rd) including both Intersections | 2023 |
11000 Block Shell Road (Steveston Hwy to Hammersmith Gate) | 2023 |
Cambie Road (No.5 Road to Jacombs Road) | 2023 |
10000 Block Wilkinson Road (No.4 R – Swinton Crescent) – both intersections included | 2023 |
12000 Block Steveston Highway (No.5 Rd to MOTI) – No.5 Road Intersection included | 2023 |
4000 Block Francis Road (No.1 Rd to Lancelot Gate) | 2023 |
5000 Block Garden City Road (Westminster Highway to Lansdowne Road) – both Intersections included PLUS MUP mill and Pave | 2023 |
11000 Block Shell Road (Steveston Hwy to Hammersmith Gate) | 2023 |
11000 Block Hammersmith Gate (Shell Road – Hammersmith Way) | 2023 |
River Road (No. 3 Road – Charles Street) | 2023 |
22000 Block Westminster Hwy (MOTI – Mclean Avenue) including Mclean intersection | 2023 |
9000 Block No.5 Road (Seacliff Road to Kingsbridge Drive) – Williams Rd and Kingsbridge Drive intersections included | 2023 |
8000 Block No.3 Road (Francis Road – Blundell Road) – Both intersections included | 2023 |
2000 Block Viking Way (Bridgeport Rd – Vulcan Way) – includes Vulcan Way intersection | 2023 |
3000 Block Jacombs Road (Cambie Road to Bathgate Way) – Both intersections included | 2023 |
13000 Block Bathgate Way (Sweden Way – Jacombs Road) – both intersections included | 2023 |
4000 Block Boundary Road (Westminster Hwy to Thompson Gate including Thompson Gate intersection PLUS MUP mill and Pave | 2023 |
No.6 Road (Cambie Road to Bridgeport Road) | 2023 |
18000 Block River Road (No.8 Road to Nelson Road) | 2023 |
Burkville Village | 2023 |
11000 Block Steveston Highway (Shell Road to Coppersmith Place) | 2023 |
River Drive – West bound lane only (No.4 Road to Van Horne Way) | 2023 |
3451 Blundell Road – Vibration Complaint | 2023 |
4480 Williams Road – Vibration Complaint | 2023 |