Construction Projects
Capital Projects Highlights
Use this interactive map to explore some of the major Engineering and Public Works projects we are working on to advance the City’s strategies. You can interact with projects that interest you through the map or the links.
Annual Asphalt Re-paving Program
Project Description
Maintenance paving will be conducted on Major Road Network (MRN) and Non-Major Road Network (Non-MRN) classified roads, which is in alignment with the City’s Ageing Infrastructure Replacement Strategy and the Pavement Management System. The project includes ancillary works such as curb, gutter, road base repairs, manhole adjustments and line painting. The re-paving program may also include, but is not limited to, the pavement component of the City’s water, sanitary, and drainage upgrade projects.
Location
Various locations throughout the City. For details, visit Paving Program.
General Considerations
- Typical hours of work will be from 7:00am to 5:00pm, Monday to Friday. Work outside of these hours may be required in some locations.
- Vehicle and pedestrian traffic may be limited at times.
- Businesses and residents will be notified in advance of work that may impact them.
Capital Funding
$6,444,071
Estimated Completion Date
Q4 2025
Project Manager
Wasim Memonwasim.memon@richmond.ca
604-276-4189
Burkeville Utility Upgrades
Project Description
The Burkeville Neighbourhood is undergoing a comprehensive drainage upgrade project that includes replacing ageing watermains, sanitary sewers, and roadways in several phases. The phasing is designed to prioritize address servicing concerns and reduce construction impacts to the community. During each phase, drainage, water, sanitary, and road infrastructure improvements within the identified phasing areas will be completed. Upgrading the drainage network will reduce local flood risks by increasing the City’s storm system capacity and better servicing the Burkeville area.
Location
Lancaster Crescent - Lysander Lane
General Considerations
- Typical hours of work will be from 7:00am to 5:00pm, Monday to Friday.
- Vehicle and pedestrian traffic may be limited at times. Residents will be notified in advance of work that may impact them.
- Vegetation removal within City right-of-way may be necessary. The City will try to avoid or minimize such impacts. If residents wish to retain and relocate the vegetation onto their property, they may do so prior to project commencement. Trees cannot be relocated without a permit from the City.
- Excavation of driveway crossings may be necessary during construction. Residents will be notified in advance of such work. Driveway crossings will be restored to original condition upon project completion.
Capital Funding
$3,000,000
Estimated Completion Date
Q4 2025
Project Manager
Roger Keatingroger.keating@richmond.ca
St. Edwards Drive Walkway Improvements
Project Description
The City of Richmond will be upgrading and widening the existing sidewalk from Bird Road to the east edge of 10211 St. Edwards Drive to improve pedestrian and cyclist safety and accessibility.
Location
St. Edwards Drive from Bird Road to the east edge of 10211 St. Edwards Drive
General Considerations
- Typical work will be from 7:00am to 5:00pm, Monday to Friday. Occasional work outside these hours may be required in some locations.
- Vehicle and pedestrian traffic may be limited at times.
- Businesses and residents will be notified in advance of the work that may impact them.
Estimated Completion Date
Completed
Project Manager
Elena PallerElena.Paller@richmond.ca
Zach Jennejohn
Zach.Jennejohn@richmond.ca
Watermain Replacement Program
Project Description
This project includes installation of a total of 4,540 m of watermain throughout the city.This will be to replace ageing water pipes with new PVC pipes as part of the City’s watermain replacement program. Watermain replacement minimizes unplanned maintenance and improves fire protection. This project is in alignment with the City’s Ageing Infrastructure Replacement Strategy.
Locations
- Sidaway Road (Blundell Road to Westminster Highway
- Francis Road (West of No. 1 Road)
- Seacote Neighbourhood
General Considerations
- Typical work will be from 7:00am to 5:00 pm, Monday to Friday. Occasional evening work may be required.
- Vehicle and pedestrian traffic may be limited at times.
- Residents will be notified in advance of the work that may impact them.
- Vegetation removal within City right-of-way may be necessary. The City will try to avoid or minimize such impacts. If you wish to retain and relocate the vegetation onto your property, you may do so prior to project commencement; however, trees cannot be relocated without a permit.
- Excavation of driveway crossings may be necessary during construction. Driveway crossings will be restored to original condition upon project completion.
Capital Funding
$8,106,000
Estimated Completion Date
Q4 2025
Project Manager
Roger Keatingroger.keating@richmond.ca
Canal Stabilization Works
Project Description
The City has identified priority locations in need of canal stabilization repair and improvements. These improvements will reduce canal servicing costs, strengthen embankments, minimize future road repairs, and improve drainage in the area.
Locations
-
Sidaway Road from Blundell Road to Westminster Highway
-
No. 7 Road from Cambie Road to 570 meters south
General Considerations
- Typical hours of work will be from 7:00am to 5:00 pm, Monday to Friday. Subject to change.
- Vehicle and pedestrian traffic may be limited at times.
- Residents will be notified in advance of work that may impact them.
Capital Funding
$2,300,000
Estimated Completion Date
Q3 2025
Project Manager
Elena PallerElena.Paller@richmond.ca
No. 2 Road & Westminster Highway Intersection Improvements
Project Description
The City of Richmond will be performing roadwork and traffic signal upgrades at the intersection of No. 2 Road and Westminster Highway to improve pedestrian and traffic safety.Location
- Intersection of No. 2 Road and Westminster Highway
General Considerations
- Typical hours of work will be from 7:00 a.m. to 5:00 p.m., Monday to Friday. Occasional work outside these hours may be required.
-
Vehicle and pedestrian traffic may be limited at times, including left and right turn restrictions.
-
Businesses and residents will be notified in advance of work that may impact them.
Estimated Completion Date
November 2025
Project Manager
Elena Paller, P.EngElena.Paller@richmond.ca
Zach Jennejohn
Zach.Jennejohn@richmond.ca
Box Culvert Repairs
Project Description
The City of Richmond’s Box Culvert Inspection Program identifies locations where settlement, cracking, and infiltration occur due to ageing box culverts. The scope of this project includes the reconstruction and rehabilitation of the box culvert on No. 4 Road, extending from Westminster Highway to Granville Road. This project involves the resealing of joints and the injection of void-filling material to mitigate the deterioration of No. 4 Road Box Culvert. Additional repair work may include, but is not limited to, patching, grouting, and structural lining. Furthermore, point repairs will be performed throughout the year as identified by the City’s Box Culvert Inspection Program.Locations
- No. 4 Road, from Westminster Highway to Granville Road
General Considerations
- Typical hours of work will be from 7:00 a.m. to 5:00 p.m., Monday to Friday. Occasional work outside of these hours may be required.
-
Vehicle and pedestrian traffic may be limited at times.
-
Residents will be notified in advance of work that may impact them.
Capital Funding
$1,500,000
Estimated Completion Date
Q4 2025
Project Manager
Roger KeatingRoger.Keating@richmond.ca
Road Safety Improvements - Westminster Highway and No. 5 Road
Project Description
The primary component of this project is the removal of the existing channelized island at the northwest corner of the intersection, to mitigate conflicts between vehicles and cyclists/pedestrians. Additional upgrades include expanding the pedestrian refuge areas and enhancing safety for pedestrians, cyclists, and transit users at the intersection. Specifically, this includes a new bus pad and sidewalk at the northwest corner, as well as enlarged pedestrian sidewalk areas at the southwest and southeast corners. It also involves the creation of new bike lanes in both eastbound and westbound directions on Westminster Highway approaching and passing through the intersection, as well as on the southbound approach of No. 5 Road.
Location
- Westminster Highway and No. 5 Road
General Considerations
- Typical hours of work will be from 7:00am – 5:00pm, Monday to Friday. Work outside of these hours may be required in some locations.
-
Vehicle and pedestrian traffic may be limited at times.
-
Businesses and residents will be notified in advance of work that may impact them.
Capital Funding
$2,475,000
Estimated Completion Date
Completed
Project Manager
Elena PallerElena.Paller@richmond.ca
Laneway Drainage Upgrades
Project Description
This project is a part of the 2025 Flood Protection Capital Program. The Flood Protection Program is developed based on the City’s long-range infrastructure replacement strategy, drainage capacity requirements, and the 2041 Official Community Plan. In order to resolve laneway drainage issues and improve access to the rear of each property, the City has implemented a program to install drainage systems and upgrade the road structure to laneways each year.
Location
- 395m of lane in the laneway west of Shell Road
- 165m of lane in the laneway east of Seagrave Road
General Considerations
- Hours of work will be from 7:00am – 5:00pm, Monday to Friday.
- There will be a full closure of the laneways, with restricted vehicular access.
- Temporary parking will be at the front of the homes.
- Garbage and recycling will be collected on the usual day; however, residents are asked to place their materials at the front of their homes for collection.
Capital Funding
$1,816,000
Estimated Completion Date
Completed
Project Manager
Wonwook YooWonwook.Yoo@richmond.ca
Gilbert Road Multi-Use Pathway
Project Description
The City of Richmond is undertaking work to enhance pedestrian and cyclist safety while providing improved accessibility through the installation of a new multi-use pathway on the east side of Gilbert Road, from Azure Road to Elmbridge Way. The scope of this project includes the construction of a new 2.7 m to 3.0 m wide multi-use pathway.
Location
- Gilbert Road from Azure Road to Elmbridge Way
General Considerations
- Typical hours of work will be from 7:00am – 5:00pm, Monday to Friday.
- Vehicle and pedestrian traffic may be limited at times.
- Residents will be notified in advance of work that may impact them.
- Excavation of driveway crossings may be necessary during construction.
- Driveway crossings will be restored to their original condition upon project completion.
Capital Funding
$4,200,000
Estimated Completion Date
Q4 2025
Project Manager
Patrick LaiPatrick.Lai@richmond.ca
9120 Westminster Highway - Frontage Improvements
Project Description
As part of the City of Richmond’s capital roadworks improvement program, the City will be upgrading roadworks, streetlighting and traffic signals at the intersection of Westminster Highway and Garden City Road, to increase pedestrian and traffic safety and movement of vehicles, cyclists and pedestrians through the intersection.
Location
- Westminster Highway and Garden City Road
General Considerations
- Typical hours of work will be from 7:00am – 5:00pm, Monday to Friday. Work outside of these hours may be required in some locations.
- Vehicle and pedestrian traffic may be limited at times.
- Businesses and residents will be notified in advance of work that may impact them.
Estimated Completion Date
October 2025
Project Manager
Elena Paller, P.EngElena.Paller@richmond.ca
Zach Jennejohn
Zach.Jennejohn@richmond.ca
Cambie and No. 4 Road - Intersection Improvements
Project Description
The intersection improvements at Cambie Road and No. 4 Road are part of the City’s continued efforts to enhance the safe and efficient movement of vehicles and pedestrians. This project will provide dedicated left-turn bays and left-turn signals in all four directions of the intersection and upgraded crosswalk painting and signage to increase road user safety.
Location
- The intersection of Cambie Road and No. 4 Road
General Considerations
- Typical hours of work will be from 7:00am – 5:00pm, Monday to Friday. Occasional work outside of these hours may be required.
- Vehicle and pedestrian traffic may be limited at times.
- Residents will be notified in advance of work that may impact them.
- Excavation of driveway crossings may be necessary during construction. Residents will be notified in advance of such work. Driveway crossings will be restored to original condition upon project completion.
Capital Funding
$1,900,000
Estimated Completion Date
Q4 2025
Project Manager
Elena Paller, P.EngElena.Paller@richmond.ca
Jessie Rehwald
Jessie.Rehwald@richmond.ca
Westbound Lane Paving - #15371 Westminster Highway to No. 7 Road
Project Description
Paving work will take place off the westbound lane on Westminster Hwy from #15371 to No. 7 Road. Construction will start on October 6, 2025, and is expected to be substantially complete by October 11, 2025.
Location
- Westbound lane on Westminster Hwy from #15371 to No. 7 Road
General Considerations
- Typical hours of work will be from 7:00am – 8:00pm, Monday to Friday and 10:00am - 8:00pm on Saturdays when required. Occasional work outside of these hours may be required.
- Vehicle and pedestrian traffic may be limited at times.
- Residents and businesses will be notified in advance of work that may impact them.
-
During the mill and pave operations, significant traffic delays are anticipated. Our goal is to reduce the impacts upon residents and businesses during these upgrades while maintaining safe working conditions for our operations and public. To minimize traffic buildup and delays, it is recommended that you plan your trip accordingly and use alternate routes. Traffic control measures will be in place to ensure safe passage of pedestrian, cyclist, and vehicle traffic.
-
Driveway access for properties located on the north side of Westminster Hwy will be affected during the course of construction. Crews will make every effort to notify the affected homeowners/residents/businesses on the day prior to the work and again in the morning. Should you require access to driveways you will be admitted by on-duty traffic control person. We ask that you not schedule any moving or pickups/drop offs that will occupy the lane during our closure.
Project Manager
Elena Paller, P.EngElena.Paller@richmond.ca